WORKED EXAMPLE — FICTIONAL, FOR DISCUSSION ONLY
Not a contract, authorisation, legal advice or a compliant change-order form.

Request DEMO-004 / Version 1 / Fictional kitchen project
Original scope: 10 square metres of white splashback tile, reference SPEC-01.
Proposed change: substitute blue tile on the same 10 square metres.
Unchanged: layout, area and installation method. Excluded: new electrical work.
Reason: client preference. Measurements and supplier availability unconfirmed.

Illustrative AUD cost reconciliation (NOT a quotation):
Added blue tile: 10 m² × A$70 = A$700 before tax
Credit original tile allowance: 10 m² × A$40 = A$400 before tax
Net before tax: A$700 - A$400 = A$300
Illustrative GST adjustment at 10%: A$30
Net increase including illustrative GST: A$330
If original total were A$20,000 including GST, illustrative revised total A$20,330.
Rates/tax are fictional assumptions. Verify applicable tax and scope separately.

Time: 2 additional working days estimated, subject to supplier confirmation.
Open question: builder to verify stock and lead time; no promised finish date.
Client response to version 1: Please keep the original white tile instead.

Version 2: original white tile retained; blue-tile upgrade omitted.
Net cost change: A$0 including illustrative GST. Extra working days: 0 expected.
Builder still confirms original tile availability.
Status: discussion acknowledged in the sample, NOT authorised work.
Formal handoff: use existing contract process if a formal record is required.
Version 1 and its response remain in history; do not overwrite them.

This example demonstrates the worksheet’s arithmetic and revision discipline.
The separate interactive demo uses its own fictional sample amounts.