How to record a renovation variation before work starts
A small change can look obvious in a text message and get confusing a week later. Was the new tile actually agreed, or did the homeowner just ask what it would cost? A variation record gives both sides one version to discuss before either side treats the change as settled.
Start here
A variation is a proposed change to what you and the builder originally agreed to do.
Before you start: Have the contract scope, the latest quote and any original allowance in front of you. An allowance is the amount already set aside for an item.
Build a decision record from the original scope
- Open the signed scope or specification and copy the reference for the item being replaced. Write one sentence on what stays unchanged so the replacement cannot quietly expand into adjacent work.
- Split the proposed price into additions and credits on the same tax basis. Ask which part is fixed, which is an allowance, and whether a delayed item changes a milestone or just a delivery date.
- Assign the quote a revision, state who still needs to respond and keep any formal approval with that revision in the contract records.
Fictional example: change VR-07
Original: S-04, 600 mm vanity. Revised: wall-hung vanity, same position.
Add A$780 + A$240 installation, less A$320 original allowance = A$700 extra, all incl. GST.
Timing: supplier says +3 business days; builder has not confirmed the effect on fit-off.
Status: v2 quoted, not approved. Next: builder confirms fit-off and exclusions.
Check before you move on: If only the total is shown, ask for the original allowance and a breakdown before treating it as final. This worksheet is a working record, not a substitute for the approval process in your contract.
For background in NSW, see the NSW Government guide to residential building contracts.
Start with the difference from the original scope
Write the original inclusion and the proposed replacement side by side. Include the work area, what stays the same, and anything the change excludes. Point to the relevant drawing, quote or selection so someone else can find the original scope.
For example: the original bathroom selection is white tile. The proposed change is blue tile on the shower wall only; the floor and other walls stay white. That is clearer than “blue tiles for the bathroom,” which leaves the area and quantity open to interpretation.
Show the cost, time and assumptions
Separate the cost of the new item from any credit for the original selection. State whether GST is included and whether the number is estimated or confirmed. Record any extra working days or dependencies separately from the price.
In this fictional example, the replacement adds A$300 including GST. It may add one working day if the supplier can deliver by Friday. Give someone responsibility for checking availability instead of presenting the timing as certain.
Keep each response with its version
If the homeowner asks to keep the original tile, record that reply against the proposal they saw. Save a new revision showing the original selection and removing the extra charge. Keep any outstanding availability question attached to the new revision.
The record supports your existing formal approval process. A worksheet entry, demo acknowledgement or chat reply is not permission to proceed. Start with the free RenoCue worksheet or open the fictional demo to see the two versions kept separately.