How to compare renovation builder quotes
Send builders the same brief, compare inclusions and allowances, and use a worked example and copyable quote request.
Send everyone the same job to price
Ask two or three suitable builders for written quotes if practical. Give each the same drawings or room list, finish expectations, site access notes and preferred timing. If one builder suggests a different design, ask them to price that as a separate option rather than substituting it in the main quote.
Copy this quote request
Hi, please quote the attached brief as written and list any alternatives separately. Please include the total with GST, key materials, disposal and protection, allowances, exclusions, expected start and duration, payment stages and quote expiry. Please flag what you cannot price until inspection and who would arrange each approval or inspection. This request is for pricing, not authorisation to start.
Read the lines where prices can change
- Fixed inclusion
- Work or an item priced in the offer, subject to the actual contract terms. Check what the price assumes.
- Prime cost allowance
- An amount set aside for a yet-to-be-chosen item, such as tiles or tapware. Check what products the allowance buys and whether fitting is separately included.
- Provisional sum
- An estimate for work the builder cannot fully price yet, such as repairing damaged timber once a wall is opened. Ask what evidence controls the adjustment and what margin applies.
- Exclusion
- Something outside the quote. It may still be needed and paid by you.
Check removal, disposal, skips, protecting floors, waterproofing, finishing, electrical or plumbing reconnections and any supply or delivery charges relevant to your job. Put unknowns in their own column. Never make a blank equal zero.
Worked example: the cheaper quote is not always cheaper
Quote A: A$32,000 including GST, disposal and tapware.
Quote B: A$29,800 including GST, plus A$1,400 disposal and A$1,200 equivalent tapware = A$32,400 on known like-for-like items. If potential floor repairs are still unpriced on both, neither total is a final outturn cost.
Compare the realistic date, who supervises, how changes are agreed, and what happens if an item is delayed. Get the clarified scope, drawings and allowances incorporated into the proposed contract, rather than relying on a verbal promise. See the NSW building contract guide.
Keep changes separate once work is underway
If the scope changes after signing, compare the extra cost or credit, timing and exact work before agreeing. Use the variation quote walkthrough and free printable change worksheet.
General homeowner information. Approval, licensing and insurance details refer to NSW, Australia. Check the current rules for your address and scope before committing. Sources checked .
Other RenoCue homeowner guides
- How to plan a home renovation in NSW
- How to find and check a renovation builder in NSW
- Builder, architect or owner-builder? A NSW guide
Use the free printable renovation change worksheet (no sign-up).
Your next step
Put two written quotes on the same scope and keep unknown costs visible. Open the side-by-side quote worksheet.